Permit notice · West Betuwe, Gelderland, Netherlands
Battery storage omgevingsvergunning application, West Betuwe (gmb-2026-268347)
Battery storage omgevingsvergunning application, West Betuwe (gmb-2026-268347) is a permit notice in West Betuwe, Gelderland, Netherlands, published 9 Jun 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | West Betuwe | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 9 Jun 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Battery storage | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.8502, 5.0200 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (environmental permit) · source
Nearby
Within 50 km of this permit notice: 696 power plants (548 operating, 6,842 MW), 118 substations, 91 CO2 emitters (53 operating), 19 data centers and 2 processing plants, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Gorinchem (C€LOGIX Participation) | Power plant | 5.6 MW | Planned | 1.2 km |
| Solar Gorinchem (Novarroofs 1) | Power plant | 2.29 MW | Operating | 1.2 km |
| 150 kV Arkel | Substation | — | — | 3.1 km |
| 150 kV substation (OSM way/165278333) | Substation | — | — | 3.1 km |
| Wind Gorinchem (Energie Groote Haar) | Power plant | 7 MW | Permitted | 3.3 km |
| Aquathermal heat Gorinchem (N.V. HVC) | CO2 emitter | — | Operating | 4.4 km |
| Biomass heat Vuren (Sonac Vuren) | CO2 emitter | — | Operating | 5.2 km |
| 150 kV Zuilichem | Substation | — | — | 9.4 km |
| Green gas Waalwijk (Wabico) | CO2 emitter | — | Operating | 16 km |
Place
Other permit notices in Gelderland
- Battery storage omgevingsplan application, Nijmegen (gmb-2025-229302)
- Battery storage omgevingsplan application, Putten (gmb-2026-343049)
- Battery storage omgevingsplan application, West Betuwe (gmb-2025-12037)
- Battery storage omgevingsplan application, West Betuwe (gmb-2026-231801)
- Battery storage omgevingsplan decision, West Betuwe (gmb-2025-88274)
- Battery storage omgevingsplan decision, West Betuwe (gmb-2026-333911)
- Battery storage omgevingsvergunning application, Apeldoorn (gmb-2025-455371)
- Battery storage omgevingsvergunning application, Apeldoorn (gmb-2025-487942)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.