Permit notice · Lelystad, Flevoland, Netherlands
Substation omgevingsvergunning application, Lelystad (gmb-2026-213751)
Substation omgevingsvergunning application, Lelystad (gmb-2026-213751) is a permit notice in Lelystad, Flevoland, Netherlands, published 6 May 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Lelystad | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 6 May 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Substation | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.5726, 5.5319 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (environmental permit) · source
Nearby
Within 50 km of this permit notice: 336 power plants (271 operating, 5,447 MW), 75 substations, 46 CO2 emitters (29 operating), 33 data centers, 2 AI supercomputers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| 150 kV Lelystad | Substation | — | — | 0.3 km |
| ENGIE Maximacentrale | CO2 emitter | 1,216,922 tCO2e | — | 0.4 km |
| Maximacentrale | Power plant | 872 MW | Operating | 0.5 km |
| 380 kV Lelystad | Substation | — | — | 0.6 km |
| Solar Lelystad (Maximazon) | Power plant | 2.49 MW | Operating | 0.8 km |
| Zonnepark IJsselmeerdijk-Lelystad | Power plant | 9.6 MW | Operating | 0.8 km |
| 150 kV Windplanblauw | Substation | — | — | 5.4 km |
| Biomass heat Lelystad (Primco BMC Lelystad) | CO2 emitter | — | Operating | 10 km |
| Green gas Biddinghuizen (De Torenhoeve Biogas) | CO2 emitter | — | Operating | 12 km |
Place
Other permit notices in Flevoland
- Battery storage omgevingsplan application, Urk (gmb-2025-265888)
- Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-178677)
- Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-490317)
- Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-65684)
- Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-94424)
- Battery storage omgevingsvergunning decision, Noordoostpolder (gmb-2025-389626)
- Battery storage omgevingsvergunning decision, Noordoostpolder (gmb-2026-485841)
- Battery storage omgevingsvergunning decision, Noordoostpolder (gmb-2026-82285)
Data on this page
- European Commission, Union Registry. EU Union Registry public data, CC BY 4.0.
- JRC Open Power Plants Database (JRC-PPDB-OPEN), European Commission, Joint Research Centre. JRC Open Power Plants Database (JRC-PPDB-OPEN), CC BY 4.0.
- Dutch power station owners' and operators' pages. Dutch power station owners' and operators' pages, Facts only, each linked to its page.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.