Permit notice · Noordoostpolder, Flevoland, Netherlands
Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-94424)
Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-94424) is a permit notice in Noordoostpolder, Flevoland, Netherlands, published 2 Mar 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Noordoostpolder | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 2 Mar 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Battery storage | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.6749, 5.9101 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (environmental permit) · source
Nearby
Within 50 km of this permit notice: 291 power plants (246 operating, 4,470 MW), 60 substations, 31 CO2 emitters (20 operating), 5 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Marknesse (CCE Solar Field Marknesse) | Power plant | 28.8 MW | Permitted | 0.9 km |
| Solar Marknesse (Zon Noordelijk Flevoland) | Power plant | 55.2 MW | Operating | 1.5 km |
| 110 kV Vollenhove | Substation | — | — | 1.7 km |
| 110 kV Noordoostpolder Voorsterweg | Substation | — | — | 1.9 km |
| Solar Marknesse (MCM Vastgoed) | Power plant | 1 MW | Operating | 4.4 km |
| Biomass heat Ens (Wouters Onroerend Goed) | CO2 emitter | — | Operating | 7.2 km |
| 110 kV Kalenbergerweg | Substation | — | — | 8.1 km |
| Green gas Luttelgeest (Peters Biogas) | CO2 emitter | — | Operating | 11 km |
| Geothermal heat IJsselmuiden (Aardwarmtecluster I KKP) | CO2 emitter | — | Operating | 11 km |
Place
Other permit notices in Flevoland
- Battery storage omgevingsplan application, Urk (gmb-2025-265888)
- Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-178677)
- Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-490317)
- Battery storage omgevingsvergunning application, Noordoostpolder (gmb-2026-65684)
- Battery storage omgevingsvergunning decision, Noordoostpolder (gmb-2025-389626)
- Battery storage omgevingsvergunning decision, Noordoostpolder (gmb-2026-485841)
- Battery storage omgevingsvergunning decision, Noordoostpolder (gmb-2026-82285)
- Data center omgevingsplan decision, Lelystad (gmb-2026-328813)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.