Heat plant · Lansingerland, South Holland, Netherlands
Geothermal heat Berkel en Rodenrijs (85 Degrees Renewable 5 - 8)
Geothermal heat Berkel en Rodenrijs (85 Degrees Renewable 5 - 8) is a permitted heat plant in Lansingerland, South Holland, Netherlands, with 33.9 MW of capacity, operated by 85 Degrees Renewable 5 - 8 B.V.
We hold more on this heat plant.Grid operator: available on request.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Lansingerland | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Grid area | Available on request | Netbeheer Nederland capaciteitskaart · Restricted · checked 25 Oct 2026 |
| Status | Permitted (SDE subsidy granted, not yet in use) | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Operator | 85 Degrees Renewable 5 - 8 B.V. | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Capacity | 33.9 MW | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Technology | Geothermal heat | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Grid operator | Available on request | Netbeheer Nederland capaciteitskaart · Restricted · checked 25 Oct 2026 |
| Coordinates | 51.9783, 4.4466 | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
Know more about this heat plant, or want an introduction to its operator? Ask us.
How it compares
Geothermal heat Berkel en Rodenrijs (85 Degrees Renewable 5 - 8) is the 3rd-largest of 10 heat plants planned, permitted or under construction in South Holland and the 4th-largest of 43 in the Netherlands by capacity; its 33.9 MW is 6.1% of the 556 MW of heat plants planned, permitted or under construction we hold for the Netherlands. It is not built yet, so it is ranked among the heat plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| South Holland | 3rd of 10 | 214 MW | 16% |
| Netherlands | 4th of 43 | 556 MW | 6.1% |
Nearby
Within 50 km of this heat plant: 540 permit notices, 537 power plants (426 operating, 9,973 MW), 155 substations, 67 data centers, 12 CO2 emitters (14,121,588 tCO2e), 6 renewable fuel plants (4 operating, 28.1 MW) and 2 processing plants, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Berkel en Rodenrijs (Sunrock Assets XII) | Power plant | 2.81 MW | Operating | 0.3 km |
| Solar Berkel en Rodenrijs (Sligro Food Group Nederland) | Power plant | 1.38 MW | Operating | 0.3 km |
| Substation omgevingsvergunning application, Lansingerland (gmb-2026-390365) | Permit notice | — | — | 0.5 km |
| Substation omgevingsvergunning decision, Lansingerland (gmb-2026-410450) | Permit notice | — | — | 0.5 km |
| Solar Berkel en Rodenrijs (Fource) | Power plant | 4.2 MW | Operating | 0.5 km |
| Grid connection instemmingsbesluit decision, Lansingerland (gmb-2025-26437) | Permit notice | — | — | 1.6 km |
| NorthC Rotterdam Zestienhoven 1&2 | Data center | — | — | 2.8 km |
| 380 kV substation (OSM way/165958261) | Substation | — | — | 3.8 km |
| Air Liquide Industrie B.V., vest. Botlek-Rotterdam | CO2 emitter | 932,483 tCO2e | — | 4.6 km |
Operator and place
Other heat plants in South Holland
- Electric boiler Rotterdam (Air Liquide Industrie)99.5 MW
- Geothermal heat Maasdijk (HVC Aardwarmte Maasdijk)60.1 MW
- Geothermal heat Naaldwijk (Trias Westland)59.2 MW
- Geothermal heat Poeldijk (Aardwarmte Vogelaer)48.5 MW
- Biomass heat Gouda (Cargill Bioindustrial)34 MW
- Geothermal heat 's-Gravenhage (Haagse Aardwarmte CR-Plein)33.3 MW
- Geothermal heat Pijnacker (Ammerlaan Geothermie)31.2 MW
- Geothermal heat Bergschenhoek (Yeager Energy Bergschenhoek 1)30.6 MW
Data on this page
- European Commission, Union Registry. EU Union Registry public data, CC BY 4.0.
- Netbeheer Nederland capaciteitskaart. Netbeheer Nederland capaciteitskaart, Restricted.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.