Grid connection · Matagorda County, Texas, United States

STP Unit2 High Pressure Turbine Upgrade grid connection (ERCOT 27INR0557)

STP Unit2 High Pressure Turbine Upgrade grid connection (ERCOT 27INR0557) is a planned grid connection in Matagorda County, Texas, United States, with 1,337 MW of capacity, held by Constellation South Texas, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMatagorda County (connects at 5915 SO_TEX__345A 345 kV)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study completed, full interconnection study started, no interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderConstellation South Texas, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity1,337 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologyNuclearERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date30 Apr 2026ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date23 Apr 2027 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

STP Unit2 High Pressure Turbine Upgrade grid connection (ERCOT 27INR0557) is the 11th-largest of 1,710 grid connections in Texas and the 45th-largest of 4,021 in the United States by capacity; its 1,337 MW is 0.14% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas11th of 1,710438,874 MW0.3%
United States45th of 4,021923,876 MW0.14%
All grid connections in our data113th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Holder, grid operator and place

Other grid connections in Texas

All 1874 grid connections in Texas, United States