Grid connection · Archer County, Texas, United States

Red Hollow Renewable Energy Solar SLF grid connection (ERCOT 28INR0088)

Red Hollow Renewable Energy Solar SLF grid connection (ERCOT 28INR0088) is a planned grid connection in Archer County, Texas, United States, with 309 MW of capacity, held by Red Hollow Renewable Energy LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationArcher County (connects at Tap 345kV (Bus# 1422) Bowman - (Bus# 17002) Garvey Road)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study completed, full interconnection study started, no interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderRed Hollow Renewable Energy LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity309 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologySolarERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date1 Jul 2024ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date19 Apr 2029 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Red Hollow Renewable Energy Solar SLF grid connection (ERCOT 28INR0088) is the 358th-largest of 1,710 grid connections in Texas and the 752nd-largest of 4,021 in the United States by capacity; its 309 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas358th of 1,710438,874 MW<0.1%
United States752nd of 4,021923,876 MW<0.1%
All grid connections in our data1,059th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

More from Red Hollow Renewable Energy LLC

Other grid connections in Texas

All 1874 grid connections in Texas, United States

Data on this page