Kilby1 Part 6 Large Block Combined Cycle grid connection (ERCOT 29INR0199) is a planned grid connection in Reeves County, Texas, United States, with 1,056 MW of capacity, held by Energy Forge One LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationReeves County (connects at #60404 Solstice Substation 345 kV)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study completed, full interconnection study started, no interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderEnergy Forge One LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity1,056 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologyNatural gasERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date25 Feb 2026ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date19 Jul 2029 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Kilby1 Part 6 Large Block Combined Cycle grid connection (ERCOT 29INR0199) is the 38th-largest of 1,710 grid connections in Texas and the 89th-largest of 4,021 in the United States by capacity; its 1,056 MW is 0.11% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas38th of 1,710438,874 MW0.24%
United States89th of 4,021923,876 MW0.11%
All grid connections in our data185th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Holder, grid operator and place