Grid connection · Goliad County, Texas, United States

Keys Hollow Solar Phase II SLF grid connection (ERCOT 24INR0065)

Keys Hollow Solar Phase II SLF grid connection (ERCOT 24INR0065) is a planned grid connection in Goliad County, Texas, United States, with 201 MW of capacity, held by Keys Hollow Solar, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationGoliad County (connects at 345kV Tap 8164 Coleto Creek - 8673 RAPTOR7A)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study completed, full interconnection study completed, interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderKeys Hollow Solar, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity201 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologySolarERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date17 Jun 2021ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date10 Mar 2028 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Keys Hollow Solar Phase II SLF grid connection (ERCOT 24INR0065) is the 896th-largest of 1,710 grid connections in Texas and the 1,565th-largest of 4,021 in the United States by capacity; its 201 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas896th of 1,710438,874 MW<0.1%
United States1,565th of 4,021923,876 MW<0.1%
All grid connections in our data1,886th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect