Alpha Power Phase 4 grid connection (ERCOT 31INR0025) is a planned grid connection in Guadalupe County, Texas, United States, with 400 MW of capacity, held by Palomino Alpha, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationGuadalupe County (connects at 345kV 7042 Zorn Substation)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study started, full interconnection study started, no interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderPalomino Alpha, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity400 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologyNatural gasERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date10 Jul 2026ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date31 Dec 2031 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Alpha Power Phase 4 grid connection (ERCOT 31INR0025) is the 268th-largest of 1,710 grid connections in Texas and the 544th-largest of 4,021 in the United States by capacity; its 400 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas268th of 1,710438,874 MW<0.1%
United States544th of 4,021923,876 MW<0.1%
All grid connections in our data847th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect