Grid connection · Starr County, Texas, United States

Bullring Wind 2 grid connection (Ercot 28INR0038)

Bullring Wind 2 grid connection (Ercot 28INR0038) is a planned grid connection in Starr County, Texas, United States, with 304 MW of capacity, held by Halcon Wind, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceBullring Wind 2 grid connection (ERCOT 28INR0038)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
LocationStarr County (connects at Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (SS completed, FIS started, IA)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderHalcon Wind, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity304 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologyWind (registered as WIN/WT)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date9 May 2024ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date30 Jun 2028 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Bullring Wind 2 grid connection (Ercot 28INR0038) is the 386th-largest of 1,710 grid connections in Texas and the 679th-largest of 3,711 in the United States by capacity; its 304 MW is <0.1% of the 833,233 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas386th of 1,710438,874 MW<0.1%
United States679th of 3,711833,233 MW<0.1%
All grid connections in our data986th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Holder, grid operator and place

More from Halcon Wind, LLC

Other grid connections in Texas

All 1874 grid connections in Texas, United States