Alamo Street BESS2 grid connection (ERCOT 26INR0734) is a planned grid connection in Pecos County, Texas, United States, with 9.99 MW of capacity, held by Momentum Pilsner, LLC.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Pecos County (connects at TSP Station Name: Alamo Street Sub TNP TSP Station Code: ALAMO_ST Load Name / Load Transformer Name: ALAMO_2 Bus #: PTI Bus Number: 38331 Voltage (Transmission level kV): 138 Node (associated w/ load/load XFMR in NMMS): 9631) | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Status | Planned (small generator, public by notice or model ready) | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Holder | Momentum Pilsner, LLC | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Capacity | 9.99 MW | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Technology | Storage | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Grid operator | Electric Reliability Council of Texas, Inc. | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Connection date | 30 Mar 2027 (proposed) | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchHow it compares
Alamo Street BESS2 grid connection (ERCOT 26INR0734) is the 1,666th-largest of 1,710 grid connections in Texas and the 3,877th-largest of 4,021 in the United States by capacity; its 9.99 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Texas | 1,666th of 1,710 | 438,874 MW | <0.1% |
| United States | 3,877th of 4,021 | 923,876 MW | <0.1% |
| All grid connections in our data | 6,029th of 7,928 | 1,372,494 MW | <0.1% |
Holder, grid operator and place
Other grid connections in Texas
- Brazos Energy Security grid connection (ERCOT 28INR0456)3,000 MW
- BM Great Rock Energy Center grid connection (ERCOT 30INR0091)1,981 MW
- Prairie Ridge (Gas - CC) grid connection (ERCOT 30INR0071)1,660 MW
- Hecate Energy Orem Wind grid connection (ERCOT 27INR0061)1,542 MW
- Aegle Power grid connection (ERCOT 27INR0084)1,536 MW
- Big Canyon Wind grid connection (ERCOT 30INR0018)1,500 MW
- Caldwell County Energy Center grid connection (ERCOT 30INR0031)1,500 MW
- Bullock Gas grid connection (ERCOT 33INR0005)1,400 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.