Grid connection · Franklin County, Texas, United States

Lazy Frog Solar SLF grid connection (ERCOT 25INR0504)

Lazy Frog Solar SLF grid connection (ERCOT 25INR0504) is a planned grid connection in Franklin County, Texas, United States, with 100 MW of capacity, held by Lazy Frog Solar, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationFranklin County (connects at 11688 Thorn Tree Switch 345kV)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study completed, full interconnection study completed, no interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderLazy Frog Solar, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity100 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologySolarERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date22 Sept 2023ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date17 Apr 2028 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Lazy Frog Solar SLF grid connection (ERCOT 25INR0504) is the 1,463rd-largest of 1,710 grid connections in Texas and the 2,677th-largest of 4,021 in the United States by capacity; its 100 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas1,463rd of 1,710438,874 MW<0.1%
United States2,677th of 4,021923,876 MW<0.1%
All grid connections in our data3,089th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

More from Lazy Frog Solar, LLC

Other grid connections in Texas

All 1874 grid connections in Texas, United States

Data on this page