Grid connection · Robertson County, Texas, United States

Buffalo Meadow Solar grid connection (ERCOT 25INR0331)

Buffalo Meadow Solar grid connection (ERCOT 25INR0331) is a planned grid connection in Robertson County, Texas, United States, with 251 MW of capacity, held by Buffalo Meadow Energy Center, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRobertson County (connects at Tap Jack Creek (975) - Twin Oak (3400) 345kV line)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study completed, full interconnection study started, no interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderBuffalo Meadow Energy Center, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity251 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologySolarERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date27 Feb 2023ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date30 Sept 2028 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Buffalo Meadow Solar grid connection (ERCOT 25INR0331) is the 558th-largest of 1,710 grid connections in Texas and the 1,110th-largest of 4,021 in the United States by capacity; its 251 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas558th of 1,710438,874 MW<0.1%
United States1,110th of 4,021923,876 MW<0.1%
All grid connections in our data1,421st of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect