Kennedy Storage grid connection (ERCOT 24INR0391) is a planned grid connection in Navarro County, Texas, United States, with 25.3 MW of capacity, held by Kennedy Bypass Solar LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNavarro County (connects at Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusPlanned (screening study completed, full interconnection study started, no interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderKennedy Bypass Solar LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity25.3 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologyStorageERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date18 Jul 2022ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date31 Dec 2028 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Kennedy Storage grid connection (ERCOT 24INR0391) is the 1,642nd-largest of 1,710 grid connections in Texas and the 3,552nd-largest of 4,021 in the United States by capacity; its 25.3 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas1,642nd of 1,710438,874 MW<0.1%
United States3,552nd of 4,021923,876 MW<0.1%
All grid connections in our data5,029th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

More from Kennedy Bypass Solar LLC

Other grid connections in Texas