Grid connection · Refugio County, Texas, United States

Charger Solar grid connection (ERCOT 23INR0047)

Charger Solar grid connection (ERCOT 23INR0047) is a grid connection under construction in Refugio County, Texas, United States, with 397 MW of capacity, held by AP Solar 4 LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRefugio County (connects at tap 345kV 8249 Angstrom – 5915 STP)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusUnder construction (screening study completed, full interconnection study completed, interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderAP Solar 4 LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity397 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologySolarERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date19 Jun 2020ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date18 Sept 2026 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Charger Solar grid connection (ERCOT 23INR0047) is the 281st-largest of 1,710 grid connections in Texas and the 613th-largest of 4,021 in the United States by capacity; its 397 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas281st of 1,710438,874 MW<0.1%
United States613th of 4,021923,876 MW<0.1%
All grid connections in our data917th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Was due to connect; the register does not list it as connected

Holder, grid operator and place

More from AP Solar 4 LLC

Other grid connections in Texas

All 1874 grid connections in Texas, United States

Data on this page