Grid connection · Robertson County, Texas, United States
Barton Branch IA grid connection (ERCOT 22INR0504)
Barton Branch IA grid connection (ERCOT 22INR0504) is a planned grid connection in Robertson County, Texas, United States, with 204 MW of capacity, held by Barton Branch IA LLC.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Robertson County (connects at Tap 345kV 3400 Twin Oak - 39950 TNP One) | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Status | Planned (screening study completed, full interconnection study completed, interconnection agreement) | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Holder | Barton Branch IA LLC | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Capacity | 204 MW | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Technology | Storage | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Grid operator | Electric Reliability Council of Texas, Inc. | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Queue date | 16 Mar 2021 | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
| Connection date | 1 Oct 2026 (proposed) | ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchLatest events
Dated events about this grid connection from official notices and registers, newest first. All recent changes.
- Entered the connection queue (the day the screening study started)
How it compares
Barton Branch IA grid connection (ERCOT 22INR0504) is the 765th-largest of 1,710 grid connections in Texas and the 1,433rd-largest of 4,021 in the United States by capacity; its 204 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Texas | 765th of 1,710 | 438,874 MW | <0.1% |
| United States | 1,433rd of 4,021 | 923,876 MW | <0.1% |
| All grid connections in our data | 1,754th of 7,928 | 1,372,494 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Was due to connect; the register does not list it as connected
Holder, grid operator and place
More from Barton Branch IA LLC
- Barton Branch IA200 MW · planned
Other grid connections in Texas
- Brazos Energy Security grid connection (ERCOT 28INR0456)3,000 MW
- BM Great Rock Energy Center grid connection (ERCOT 30INR0091)1,981 MW
- Prairie Ridge (Gas - CC) grid connection (ERCOT 30INR0071)1,660 MW
- Hecate Energy Orem Wind grid connection (ERCOT 27INR0061)1,542 MW
- Aegle Power grid connection (ERCOT 27INR0084)1,536 MW
- Big Canyon Wind grid connection (ERCOT 30INR0018)1,500 MW
- Caldwell County Energy Center grid connection (ERCOT 30INR0031)1,500 MW
- Bullock Gas grid connection (ERCOT 33INR0005)1,400 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.