Grid connection · Brazoria County, Texas, United States

Cottonwood Bayou Solar grid connection (ERCOT 19INR0134)

Cottonwood Bayou Solar grid connection (ERCOT 19INR0134) is a grid connection under construction in Brazoria County, Texas, United States, with 351 MW of capacity, held by Cottonwood Bayou Solar, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBrazoria County (connects at tap 138kV 42870 Liverpool - 43070 Petson)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusUnder construction (screening study completed, full interconnection study completed, interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderCottonwood Bayou Solar, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity351 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologySolarERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date22 Sept 2017ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date30 Oct 2026 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Cottonwood Bayou Solar grid connection (ERCOT 19INR0134) is the 309th-largest of 1,710 grid connections in Texas and the 658th-largest of 4,021 in the United States by capacity; its 351 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas309th of 1,710438,874 MW<0.1%
United States658th of 4,021923,876 MW<0.1%
All grid connections in our data963rd of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

More from Cottonwood Bayou Solar, LLC

Other grid connections in Texas

All 1874 grid connections in Texas, United States

Data on this page