Grid connection · Starr County, Texas, United States

Mesteno Wind grid connection (ERCOT 16INR0081)

Mesteno Wind grid connection (ERCOT 16INR0081) is a grid connection under construction in Starr County, Texas, United States, with 202 MW of capacity, held by Mesteno Windpower, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationStarr County (connects at 80355 Del Sol 345kV)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusUnder construction (screening study completed, full interconnection study completed, interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderMesteno Windpower, LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Capacity202 MWERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologyWindERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date30 Dec 2014ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date1 Mar 2027 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

How it compares

Mesteno Wind grid connection (ERCOT 16INR0081) is the 814th-largest of 1,710 grid connections in Texas and the 1,483rd-largest of 4,021 in the United States by capacity; its 202 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Texas814th of 1,710438,874 MW<0.1%
United States1,483rd of 4,021923,876 MW<0.1%
All grid connections in our data1,804th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

Other grid connections in Texas

All 1874 grid connections in Texas, United States

Data on this page