Grid connection · Trumbull County, Ohio, United States

Lordstown Energy Center 1 CC grid connection (PJM AH1-706)

Lordstown Energy Center 1 CC grid connection (PJM AH1-706) is a planned grid connection in Trumbull County, Ohio, United States, with 30.5 MW of capacity, held by Clean Energy Future - Lordstown, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTrumbull County (connects at Lordstown 345 kV)PJM New Services Queue · Free reuse · checked 24 Oct 2026
StatusPlanned (engineering and procurement, cluster TC2 Final Agreement)PJM New Services Queue · Free reuse · checked 24 Oct 2026
HolderClean Energy Future - Lordstown, LLCPJM New Services Queue · Free reuse · checked 24 Oct 2026
Capacity30.5 MWPJM New Services Queue · Free reuse · checked 24 Oct 2026
TechnologyNatural gasPJM New Services Queue · Free reuse · checked 24 Oct 2026
Grid operatorPJM Interconnection, L.L.C.PJM New Services Queue · Free reuse · checked 24 Oct 2026
Queue date7 Apr 2025PJM New Services Queue · Free reuse · checked 24 Oct 2026
Connection date22 Nov 2027 (proposed)PJM New Services Queue · Free reuse · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue

How it compares

Lordstown Energy Center 1 CC grid connection (PJM AH1-706) is the 170th-largest of 216 grid connections in Ohio and the 3,507th-largest of 4,021 in the United States by capacity; its 30.5 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Ohio170th of 21644,307 MW<0.1%
United States3,507th of 4,021923,876 MW<0.1%
All grid connections in our data4,836th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

More from Clean Energy Future - Lordstown, LLC

Other grid connections in Ohio

All 216 grid connections in Ohio, United States

Data on this page