Grid connection · Northampton County, North Carolina, United States
Northampton 34.5 kV grid connection (PJM C01-1662)
Northampton 34.5 kV grid connection (PJM C01-1662) is a planned grid connection in Northampton County, North Carolina, United States, with 7 MW of capacity, held by Fall Line Solar Farm, LLC.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Northampton County (connects at Northampton 34.5 kV) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Status | Planned (active, cluster C01 Phase 1) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Holder | Fall Line Solar Farm, LLC | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Capacity | 7 MW | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Technology | Solar (registered as Solar) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Grid operator | PJM Interconnection, L.L.C. | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Queue date | 27 Apr 2026 | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Connection date | 25 Aug 2028 (proposed) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchHow it compares
Northampton 34.5 kV grid connection (PJM C01-1662) is the 35th-largest of 37 grid connections in North Carolina and the 3,636th-largest of 3,711 in the United States by capacity; its 7 MW is <0.1% of the 833,233 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| North Carolina | 35th of 37 | 4,069 MW | 0.17% |
| United States | 3,636th of 3,711 | 833,233 MW | <0.1% |
| All grid connections in our data | 6,005th of 7,616 | 1,281,251 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Holder, grid operator and place
Other grid connections in North Carolina
- Earleys - Cashie 230 kV grid connection (PJM C01-1727)450 MW
- Suffolk - Nucor Tap 230 kV grid connection (PJM C01-1499)375 MW
- Macadamia Solar grid connection (PJM AD1-074)300 MW
- Hogard Mill - Earleys 230 kV grid connection (PJM C01-2143)200 MW
- Cherry Solar grid connection (PJM AC1-086)180 MW
- Suffolk - Nucor Tap 230 kV grid connection (PJM C01-2144)166 MW
- Cashie - Earleys 230 kV grid connection (PJM C01-1301)150 MW
- Mackeys - Creswell 115 kV grid connection (PJM AH1-040 - moved to TC2)150 MW
Data on this page
- California ISO. Checked 2026-10-24. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.