Grid connection · Richmond County, New York, United States

Elevate Arthur Kill II grid connection (NYISO C24-131)

Elevate Arthur Kill II grid connection (NYISO C24-131) is a planned grid connection in Richmond County, New York, United States, with 180 MW of capacity, held by Lighthouse Arthur Kill II, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRichmond County (connects at Fresh Kills 345 kV substation)NYISO interconnection queue · Free reuse · checked 24 Oct 2026
StatusPlanned (cluster status 7, cluster Cluster 2024)NYISO interconnection queue · Free reuse · checked 24 Oct 2026
HolderLighthouse Arthur Kill II, LLCNYISO interconnection queue · Free reuse · checked 24 Oct 2026
Capacity180 MWNYISO interconnection queue · Free reuse · checked 24 Oct 2026
TechnologyStorageNYISO interconnection queue · Free reuse · checked 24 Oct 2026
Grid operatorNew York Independent System Operator, Inc.NYISO interconnection queue · Free reuse · checked 24 Oct 2026
Queue date5 Sept 2024NYISO interconnection queue · Free reuse · checked 24 Oct 2026
Connection date1 Jun 2030 (proposed)NYISO interconnection queue · Free reuse · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue

How it compares

Elevate Arthur Kill II grid connection (NYISO C24-131) is the 62nd-largest of 212 grid connections in New York and the 1,904th-largest of 4,021 in the United States by capacity; its 180 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
New York62nd of 21233,437 MW0.54%
United States1,904th of 4,021923,876 MW<0.1%
All grid connections in our data2,239th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place