Grid connection · Clark County, Nevada, United States

Bonanza Solar grid connection (CAISO 1649)

Bonanza Solar grid connection (CAISO 1649) is a planned grid connection in Clark County, Nevada, United States, with 300 MW of capacity, connected by California Independent System Operator Corporation.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceBONANZA SOLAR grid connection (CAISO 1649)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
LocationClark County (connects at Innovation Substation 230 kV), Nye County (connects at Innovation Substation 230 kV)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
StatusPlanned (active; interconnection agreement executed, cluster C12)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Capacity300 MWCAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
TechnologySolar (registered as Storage Battery / Photovoltaic Solar)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
TechnologyStorage (registered as Storage Battery / Photovoltaic Solar)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Grid operatorCalifornia Independent System Operator CorporationCAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Queue date15 Apr 2019CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Connection date30 Sept 2028 (proposed)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue

How it compares

Bonanza Solar grid connection (CAISO 1649) is the 23rd-largest of 53 grid connections in Nevada and the 849th-largest of 4,021 in the United States by capacity; its 300 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Nevada23rd of 5316,392 MW1.8%
United States849th of 4,021923,876 MW<0.1%
All grid connections in our data1,156th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Grid operator and place

More from California Independent System Operator Corporation

Other grid connections in Nevada

All 53 grid connections in Nevada, United States

Data on this page