Grid connection · England, United Kingdom
Torpoint Mendennick grid connection
Torpoint Mendennick grid connection is a grid connection in England, United Kingdom.
We hold more on this right.Capacity, connection date, grid operator, holder, location, status, technology and voltage: available on request.
Request this dataFacts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | TORPOINT MENDENNICK grid connection | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Location | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Status | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Holder | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Capacity | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Technology | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Grid operator | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Connection date | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Voltage | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Coordinates | 50.3558, -4.2389 | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its owner? Ask us.
Nearby
Within 50 km of this grid connection: 187 power plants (96 operating, 580 MW) and 1 mine, measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Mendennick Wind Farm | Power plant | 2.6 MW | Cancelled | 0.0 km |
| Mendennick Farm | Power plant | 2.8 MW | Operating | 0.1 km |
| Anthony Estate Solar Farm | Power plant | 4.7 MW | Operating | 0.9 km |
| Tungsten West | Mine | — | — | 17 km |
Place
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- © European Union, European Commission (DG GROW). EU CRMA strategic projects, CC BY 4.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.