Data center, Ocean County (OSM way 1549253249) is a data center in Ocean County, New Jersey, United States, with a 273,268 m² site. It is in an area of medium to high water stress.
Power and water
Water stress here is medium to high: withdrawals take 29.6% of the renewable water supply of its sub-basin (WRI Aqueduct 4.0, baseline, score 2.6 of 5).
Distances run between the points of the records. How the grid and plants nearby are found; water stress from WRI Aqueduct 4.0.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Ocean County, New Jersey | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Water stress | Medium to high (20–40%) (score 2.6 of 5, withdrawals 29.6% of renewable supply) | WRI Aqueduct 4.0 · CC BY 4.0 · checked 25 Oct 2026 |
| Building footprint | 273,268 m² (site outline) | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Coordinates | 40.0426, -74.2795 | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
Research on this data center and its owner.Who owns it up to the parent company, its power supply, grid connection and planning status, and an introduction to the owner.
Request researchNearby
Within 50 km of this data center: 5 power plants (2 operating, 2,159 MW), 2 mines and 2 AI supercomputers, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| NAEA Lakewood LLC | Power plant | 288 MW | Idle | 9.7 km |
| Empire Blended Products Inc | Mine | — | Operating | 17 km |
| Oyster Creek | Power plant | 550 MW | Closed | 26 km |
| Fairless Energy Center | Power plant | 1,338 MW | Operating | 41 km |
| Princeton Della Phase 1 | AI supercomputer | 100 H100e | Operating | 44 km |
| Princeton Della Phase 2 | AI supercomputer | 396 H100e | Operating | 44 km |
| Kingston Quarry | Mine | — | Operating | 48 km |
Place
Other data centers in New Jersey
Data on this page
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI supercomputers, CC BY 4.0.
- MSHA Mines Data Set. MSHA Mines Data Set, Public domain.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Kuzma, S., M.F.P. Bierkens, S. Lakshman, T. Luo, L. Saccoccia, E. H. Sutanudjaja, and R. Van Beek. 2023. Aqueduct 4.0: Updated Decision-Relevant Global Water Risk Indicators. Technical Note. Washington, DC: World Resources Institute. doi.org/10.46830/writn.23.00061. WRI Aqueduct 4.0, CC BY 4.0.