AI supercomputer · Oklahoma, United States

Google Oklahoma TPU v4 Pods

Google Oklahoma TPU v4 Pods is an AI supercomputer in Oklahoma, United States, with 4,553 H100e of compute, owned by Google.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationOklahomaEpoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
Address4581 Webb St, Pryor, OK 74361Epoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
StatusOperatingEpoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
Part ofGoogle Pryor (North) (matched by address+name+operator)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Start year2022Epoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
Owner typePrivateEpoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
OwnerGoogleEpoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
Compute (H100 equivalents)4,553 H100eEpoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
ChipsGoogle TPU v4Epoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
AI chips32,768Epoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
Facility power23.7 MW (estimated)Epoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026
Coordinates36.2412, -95.3300Epoch AI supercomputers · CC BY 4.0 · checked 24 Oct 2026

Research on this AI supercomputer and its owner.Who owns it up to the parent company, the data center it runs in, its power supply and who uses it, and an introduction to the owner.

Request research

How it compares by compute

Google Oklahoma TPU v4 Pods is the 25th-largest of 118 AI supercomputers in the United States by compute, with 4,553 H100e. Ranks and totals cover the AI supercomputers in our data that report their compute, not every one in existence.

WithinRank
United States25th of 118
All AI supercomputers in our data35th of 284

Nearby

Within 50 km of this AI supercomputer: 8 power plants (4 operating, 4,955 MW), 2 data centers (1 operating, 368 MW) and 2 mines, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Google Pryor (North)Data center368 MWOperating0.7 km
ChouteauPower plant1,070 MWOperating5.2 km
Huckleberry SolarPower plant125 MWUnder construction6.2 km
GRECPower plant1,194 MWOperating6.7 km
Lone Star Pryor PLT Mill & QYMine—Operating29 km
Choska Sand PlantMine—Operating47 km
TulsaConnect DC3Data center——48 km