Power plant · Badem, Rhineland-Palatinate, Germany

PVA Badem II

PVA Badem II is a planned solar power plant in Badem, Rhineland-Palatinate, Germany, with 15 MW of capacity, operated by TEP Fortuna GmbH & Co. KG.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBademMarktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
Address54657 BademMarktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
StatusPlannedMarktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
OperatorTEP Fortuna GmbH & Co. KGMarktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
Capacity15 MWMarktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
TechnologySolarMarktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
Grid operatorWestnetz GmbHMarktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
Grid connection levelHigh voltage (110 kV) (Hochspannung)Marktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026
Coordinates50.0159, 6.5958Marktstammdatenregister · record · DL-DE-BY-2.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

PVA Badem II is the 62nd-largest of 124 power plants planned, permitted or under construction in Rhineland-Palatinate and the 1,446th-largest of 2,173 in Germany by capacity; its 15 MW is <0.1% of the 78,152 MW of power plants planned, permitted or under construction we hold for Germany. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Rhineland-Palatinate62nd of 1243,015 MW0.5%
Germany1,446th of 2,17378,152 MW<0.1%
All power plants planned, permitted or under construction in our data4,090th of 5,799657,076 MW<0.1%

Nearby

Within 50 km of this power plant: 58 substations and 1 CO2 emitter (160,011 tCO2e), measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.

NameKindSizeStatusDistance
110 kV substation (OSM way/1495050515)Substation——1.3 km
Station KyllburgSubstation——1.8 km
Station BitburgSubstation——7.1 km
Drehrohrofenanlage ÜxheimCO2 emitter160,011 tCO2e—38 km

Operator, grid operator and place

Other power plants in Rhineland-Palatinate

All 352 power plants in Rhineland-Palatinate, Germany

Data on this page