Permit notice · Soest, Utrecht, Netherlands
Battery storage omgevingsvergunning decision, Soest (gmb-2026-467295)
Battery storage omgevingsvergunning decision, Soest (gmb-2026-467295) is a permit notice in Soest, Utrecht, Netherlands, published 7 Oct 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Soest | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 7 Oct 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Battery storage | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.1936, 5.2898 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 507 power plants (398 operating, 6,170 MW), 88 substations, 86 data centers, 54 CO2 emitters (33 operating), 2 AI supercomputers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| 150 kV Soest | Substation | — | — | 4.6 km |
| Aquathermal heat Amersfoort (Duurzaam Opwekken Amersfoort) | CO2 emitter | — | Planned | 4.7 km |
| Biomass Amersfoort (Waterschap Vallei en Veluwe) | Power plant | 1.5 MW | Operating | 4.7 km |
| Solar Eemnes (International Solar Projects IV) | Power plant | 5.66 MW | Operating | 5.0 km |
| Solar Bunschoten-Spakenburg (Rooftop Energy) | Power plant | 15 MW | Operating | 6.2 km |
| Biomass heat Hilversum (Begreen Energy) | CO2 emitter | — | Operating | 7.2 km |
| Geothermal heat Amersfoort (Aardwarmte Amersfoort) | CO2 emitter | — | Cancelled | 7.9 km |
| 150 kV Bunschoten | Substation | — | — | 9.4 km |
| Eurofiber data center Utrecht 1 | Data center | — | — | 13 km |
Place
Other permit notices in Utrecht
- Battery storage omgevingsvergunning application, Amersfoort (gmb-2025-177635)
- Battery storage omgevingsvergunning application, Amersfoort (gmb-2025-185284)
- Battery storage omgevingsvergunning application, Amersfoort (gmb-2026-38544)
- Battery storage omgevingsvergunning application, Amersfoort (gmb-2026-494575)
- Battery storage omgevingsvergunning application, Amersfoort (gmb-2026-494693)
- Battery storage omgevingsvergunning application, Amersfoort (gmb-2026-82709)
- Battery storage omgevingsvergunning application, Amersfoort (gmb-2026-94183)
- Battery storage omgevingsvergunning application, De Ronde Venen (gmb-2026-111718)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.