Permit notice · Krimpenerwaard, South Holland, Netherlands
Grid connection omgevingsvergunning decision, Krimpenerwaard (gmb-2025-62974)
Grid connection omgevingsvergunning decision, Krimpenerwaard (gmb-2025-62974) is a permit notice in Krimpenerwaard, South Holland, Netherlands, published 14 Feb 2025.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Krimpenerwaard | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 14 Feb 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Grid connection | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.9613, 4.7770 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 702 power plants (558 operating, 11,730 MW), 171 substations, 113 CO2 emitters (60 operating), 89 data centers, 2 processing plants and 2 AI supercomputers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Bergambacht (AVE Vastgoed) | Power plant | 1.02 MW | Operating | 2.1 km |
| Solar Bergambacht (Solar EGP NL South) | Power plant | 1.8 MW | Operating | 3.5 km |
| 150 kV Gouda | Substation | — | — | 5.9 km |
| Heat pump Gouda (Compaxo Leasing Gouda) | CO2 emitter | — | Operating | 6.8 km |
| Biomass Gouda (Cargill Bioindustrial) | Power plant | 4.39 MW | Operating | 6.9 km |
| Biomass heat Gouda (Cargill Bioindustrial) | CO2 emitter | — | Operating | 6.9 km |
| Heat pump Bleskensgraaf Ca (Zuivelcoöperatie Deltamilk BA) | CO2 emitter | — | Operating | 10 km |
| 380 kV Krimpen a/d IJssel | Substation | — | — | 11 km |
| 150 kV Krimpen a/d IJssel | Substation | — | — | 12 km |
Place
Other permit notices in South Holland
- Battery storage omgevingsplan application, Midden-Delfland (gmb-2026-166439)
- Battery storage omgevingsplan application, Nieuwkoop (gmb-2026-286452)
- Battery storage omgevingsplan application, Rotterdam (gmb-2026-427260)
- Battery storage omgevingsplan decision, Kaag en Braassem (gmb-2025-123830)
- Battery storage omgevingsplan decision, Kaag en Braassem (gmb-2026-395920)
- Battery storage omgevingsplan decision, Lisse (gmb-2026-93012)
- Battery storage omgevingsplan decision, Midden-Delfland (gmb-2026-210961)
- Battery storage omgevingsplan decision, Nieuwkoop (gmb-2026-346519)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.