Permit notice · Lansingerland, South Holland, Netherlands
Battery storage omgevingsvergunning decision, Lansingerland (gmb-2026-445696)
Battery storage omgevingsvergunning decision, Lansingerland (gmb-2026-445696) is a permit notice in Lansingerland, South Holland, Netherlands, published 23 Sept 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Lansingerland | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 23 Sept 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Battery storage | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.9837, 4.5296 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its applicant.Who is behind it up to the parent company, the decision and the asset it is for, and an introduction to the applicant.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 583 power plants (460 operating, 10,282 MW), 160 substations, 89 CO2 emitters (49 operating), 76 data centers and 2 processing plants, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Geothermal heat Bergschenhoek (Yeager Energy Bergschenhoek Holding) | CO2 emitter | — | Permitted | 1.0 km |
| Geothermal heat Bergschenhoek (Yeager Energy Bergschenhoek 1) | CO2 emitter | — | Operating | 2.3 km |
| Solar Bergschenhoek (Trio Solar 5) | Power plant | 19.2 MW | Cancelled | 2.3 km |
| Centrale RoCa | Power plant | 264 MW | Operating | 2.5 km |
| Geothermal heat Bergschenhoek (Yeager Energy Bergschenhoek Holding) | CO2 emitter | — | Permitted | 2.6 km |
| Solar Bleiswijk (Anthura) | Power plant | 1.25 MW | Operating | 3.1 km |
| 150 kV Rotterdam Ommoord | Substation | — | — | 3.2 km |
| 380 kV substation (OSM way/165958261) | Substation | — | — | 5.8 km |
| 380 kV Bleiswijk | Substation | — | — | 5.8 km |
Place
Other permit notices in South Holland
- Battery storage omgevingsplan application, Midden-Delfland (gmb-2026-166439)
- Battery storage omgevingsplan application, Nieuwkoop (gmb-2026-286452)
- Battery storage omgevingsplan application, Rotterdam (gmb-2026-427260)
- Battery storage omgevingsplan decision, Kaag en Braassem (gmb-2025-123830)
- Battery storage omgevingsplan decision, Kaag en Braassem (gmb-2026-395920)
- Battery storage omgevingsplan decision, Lisse (gmb-2026-93012)
- Battery storage omgevingsplan decision, Midden-Delfland (gmb-2026-210961)
- Battery storage omgevingsplan decision, Nieuwkoop (gmb-2026-346519)
Data on this page
- JRC Open Power Plants Database (JRC-PPDB-OPEN), European Commission, Joint Research Centre. JRC Open Power Plants Database (JRC-PPDB-OPEN), CC BY 4.0.
- Dutch power station owners' and operators' pages. Dutch power station owners' and operators' pages, Facts only, each linked to its page.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.