Permit notice · Edam-Volendam, North Holland, Netherlands
Substation omgevingsvergunning application, Edam-Volendam (gmb-2026-105877)
Substation omgevingsvergunning application, Edam-Volendam (gmb-2026-105877) is a permit notice in Edam-Volendam, North Holland, Netherlands, published 9 Mar 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Edam-Volendam | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 9 Mar 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Substation | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.5766, 5.0026 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (environmental permit) · source
Nearby
Within 50 km of this permit notice: 351 power plants (292 operating, 6,409 MW), 88 data centers, 77 substations, 50 CO2 emitters (29 operating), 2 AI supercomputers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Oosthuizen (Hoogheemraadschap Hollands Noorderkwartier) | Power plant | 2.28 MW | Operating | 0.7 km |
| Windpark Lijsbeth Tijs Holding | Power plant | 5.1 MW | Operating | 6.2 km |
| Solar Purmerend (Alleco Solar Energy) | Power plant | 5.6 MW | Operating | 6.3 km |
| Biomass heat Purmerend (SVP Holding) | CO2 emitter | — | Operating | 7.4 km |
| Geothermal heat Purmerend (Yeager Energy) | CO2 emitter | — | Planned | 8.3 km |
| 150 kV Wijdewormer | Substation | — | — | 10 km |
| Green gas Hensbroek (Green Energy Koggenland) | CO2 emitter | — | Operating | 11 km |
| 150 kV Oterleek | Substation | — | — | 13 km |
| 150 kV Westwoud | Substation | — | — | 15 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.