Permit notice · Velsen, North Holland, Netherlands
Nitrogen natuurvergunning application, Velsen (prb-2025-7823)
Nitrogen natuurvergunning application, Velsen (prb-2025-7823) is a permit notice in Velsen, North Holland, Netherlands, published 15 May 2025.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Velsen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 15 May 2025 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.4457, 4.6439 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its applicant.Who is behind it up to the parent company, the decision and the asset it is for, and an introduction to the applicant.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (nature permit) · source
Nearby
Within 50 km of this permit notice: 343 power plants (274 operating, 4,469 MW), 92 substations, 90 data centers, 56 CO2 emitters (33 operating) and 2 AI supercomputers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Opstijgpunt Velsen-zuid | Substation | — | — | 2.0 km |
| Electric boiler Velsen-Noord (Eneco Heat Production & Industrials) | CO2 emitter | — | Planned | 2.4 km |
| Solar Velsen-Noord (Lineage Velsen PropCo) | Power plant | 1.38 MW | Operating | 2.6 km |
| Opstijgpunt Beverwijk | Substation | — | — | 2.6 km |
| 150 kV Velsen | Substation | — | — | 2.9 km |
| Solar Velsen-Noord (DekaMarkt Groep) | Power plant | 3.08 MW | Operating | 3.0 km |
| Vattenfall Power Velsen | CO2 emitter | 3,745,786 tCO2e | — | 3.0 km |
| Solar Velsen-Noord (LAG Velsen) | Power plant | 2 MW | Operating | 3.2 km |
| Vattenfall Power IJmond | CO2 emitter | 1,398,891 tCO2e | — | 3.5 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- European Commission, Union Registry. EU Union Registry public data, CC BY 4.0.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.