Permit notice · Castricum, North Holland, Netherlands
Nitrogen natuurvergunning application, Castricum (prb-2026-6694)
Nitrogen natuurvergunning application, Castricum (prb-2026-6694) is a permit notice in Castricum, North Holland, Netherlands, published 20 Apr 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Castricum | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 20 Apr 2026 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.5564, 4.6517 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (nature permit) · source
Nearby
Within 50 km of this permit notice: 284 power plants (235 operating, 3,817 MW), 86 data centers, 75 substations, 44 CO2 emitters (23 operating) and 2 AI supercomputers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Energiepark Uitgeest | Power plant | 15 MW | Permitted | 4.6 km |
| Solar Uitgeest (Coöperatieve Windenergie Vereniging 'Kennemerwind U.A.') | Power plant | 1 MW | Cancelled | 4.6 km |
| Solar Uitgeest (Duurzaam Uitgeest Energie Coöperatie) | Power plant | 1 MW | Cancelled | 4.6 km |
| Geothermal heat Heemskerk (Schoone Orchideeen Research & Development) | CO2 emitter | — | Operating | 5.2 km |
| 150 kV substation (OSM way/1252160893) | Substation | — | — | 7.5 km |
| 380 kV Wijk aan Zee | Substation | — | — | 8.0 km |
| 380 kV Hollandse Kust Noord Landstation | Substation | — | — | 8.0 km |
| Green gas Alkmaar (ENGIE RGE Alkmaar) | CO2 emitter | — | Operating | 8.5 km |
| Green gas Alkmaar (SCW Systems) | CO2 emitter | — | Operating | 8.5 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.