Permit notice · Velsen, North Holland, Netherlands
Grid connection omgevingsvergunning decision, Velsen (prb-2024-17488)
Grid connection omgevingsvergunning decision, Velsen (prb-2024-17488) is a permit notice in Velsen, North Holland, Netherlands, published 15 Nov 2024, applied for by Tata Steel IJmuiden B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Velsen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 15 Nov 2024 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | Tata Steel IJmuiden B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Grid connection | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.4739, 4.6205 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its applicant.Who is behind it up to the parent company, the decision and the asset it is for, and an introduction to the applicant.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 316 power plants (259 operating, 3,928 MW), 87 data centers, 85 substations, 45 CO2 emitters (25 operating) and 2 AI supercomputers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Vattenfall Power IJmond | CO2 emitter | 1,398,891 tCO2e | — | 0.1 km |
| Centrale Velsen | Power plant | 869 MW | Operating | 0.2 km |
| Vattenfall Power Velsen | CO2 emitter | 3,745,786 tCO2e | — | 0.6 km |
| Solar Velsen-Noord (LAG Velsen) | Power plant | 2 MW | Operating | 0.7 km |
| 150 kV Velsen | Substation | — | — | 0.8 km |
| Electric boiler Velsen-Noord (Eneco Heat Production & Industrials) | CO2 emitter | — | Planned | 1.4 km |
| 150 kV substation (OSM way/165095020) | Substation | — | — | 1.4 km |
| 380 kV Wijk aan Zee | Substation | — | — | 1.4 km |
| Windpark Spuisluis | Power plant | 20.7 MW | Operating | 1.6 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- European Commission, Union Registry. EU Union Registry public data, CC BY 4.0.
- JRC Open Power Plants Database (JRC-PPDB-OPEN), European Commission, Joint Research Centre. JRC Open Power Plants Database (JRC-PPDB-OPEN), CC BY 4.0.
- Dutch power station owners' and operators' pages. Dutch power station owners' and operators' pages, Facts only, each linked to its page.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.