Permit notice · Cranendonck, North Brabant, Netherlands
Substation omgevingsvergunning application, Cranendonck (prb-2026-14570)
Substation omgevingsvergunning application, Cranendonck (prb-2026-14570) is a permit notice in Cranendonck, North Brabant, Netherlands, published 27 Aug 2026, applied for by Enexis Netbeheer B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Cranendonck | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 27 Aug 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | Enexis Netbeheer B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Substation | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.3173, 5.6319 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (environmental permit) · source
Nearby
Within 50 km of this permit notice: 456 power plants (332 operating, 3,463 MW), 78 substations, 41 CO2 emitters (30 operating) and 10 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| 150 kV Maarheeze | Substation | — | — | 0.1 km |
| Solar Maarheeze (International Solar Projects III) | Power plant | 1.37 MW | Operating | 1.7 km |
| Zonnepark Aardbrandsven | Power plant | 75 MW | Permitted | 2.0 km |
| Zonnepark Budel Dorplein II | Power plant | 58 MW | Permitted | 2.0 km |
| Green gas Sterksel (Blue Sphere Brabant) | CO2 emitter | — | Operating | 3.3 km |
| 150 kV Weertheide | Substation | — | — | 8.0 km |
| Electric boiler Weert (Trespa International) | CO2 emitter | — | Planned | 8.3 km |
| 150 kV Budel | Substation | — | — | 8.8 km |
| Biomass heat Someren (Peelpluim) | CO2 emitter | — | Operating | 9.2 km |
Place
Other permit notices in North Brabant
- Battery storage omgevingsplan application, Bergeijk (gmb-2025-54004)
- Battery storage omgevingsplan application, Reusel-De Mierden (gmb-2026-479275)
- Battery storage omgevingsplan decision, Bergeijk (gmb-2025-256724)
- Battery storage omgevingsplan decision, Gemert-Bakel (gmb-2026-211754)
- Battery storage omgevingsplan decision, Laarbeek (gmb-2025-567631)
- Battery storage omgevingsplan decision, Oisterwijk (gmb-2025-573841)
- Battery storage omgevingsvergunning application, 's-Hertogenbosch (gmb-2026-438078)
- Battery storage omgevingsvergunning application, Altena (gmb-2026-248644)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.