Permit notice · Leudal, Limburg, Netherlands
Nitrogen natuurvergunning draft decision, Leudal (prb-2026-8966)
Nitrogen natuurvergunning draft decision, Leudal (prb-2026-8966) is a permit notice in Leudal, Limburg, Netherlands, published 29 May 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Leudal | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 29 May 2026 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Draft decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.2420, 5.8769 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Draft decision (nature permit) · source
Nearby
Within 50 km of this permit notice: 495 power plants (346 operating, 3,980 MW), 111 substations, 34 CO2 emitters (28 operating) and 10 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| 150 kV Kelpen | Substation | — | — | 4.3 km |
| Solar Nunhem (Zonneparken Leudal Energie) | Power plant | 2.05 MW | Operating | 5.1 km |
| Biomass heat Roggel (Doehler Roggel) | CO2 emitter | — | Operating | 5.3 km |
| Solar Haelen (One Solar Beheer VIII) | Power plant | 2.07 MW | Planned | 6.5 km |
| 150 kV Buggenum | Substation | — | — | 6.7 km |
| Biomass Heythuysen (Holmel) | Power plant | 3.32 MW | Operating | 6.7 km |
| Green gas Heythuysen (Holmel) | CO2 emitter | — | Operating | 6.7 km |
| Biomass heat Neer (Pluimveebedrijf Beenders) | CO2 emitter | — | Operating | 6.9 km |
| 150 kV Roermond | Substation | — | — | 9.5 km |
Place
Other permit notices in Limburg
- Battery storage omgevingsvergunning application, Beek (gmb-2025-3841)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2025-514872)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2026-288455)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2026-288464)
- Battery storage omgevingsvergunning application, Heerlen (gmb-2025-258802)
- Battery storage omgevingsvergunning application, Heerlen (gmb-2026-376025)
- Battery storage omgevingsvergunning application, Landgraaf (gmb-2024-476613)
- Battery storage omgevingsvergunning application, Leudal (gmb-2025-567734)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.