Permit notice · Westerwolde, Groningen, Netherlands
Nitrogen natuurvergunning draft decision, Westerwolde (prb-2026-17065)
Nitrogen natuurvergunning draft decision, Westerwolde (prb-2026-17065) is a permit notice in Westerwolde, Groningen, Netherlands, published 7 Oct 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Westerwolde | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 7 Oct 2026 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Draft decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 53.0241, 7.1420 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Draft decision (nature permit) · source
Nearby
Within 50 km of this permit notice: 309 power plants (227 operating, 7,987 MW), 142 substations, 24 CO2 emitters (14 operating) and 7 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Zonnepark Ter Apelkanaal | Power plant | 15.3 MW | Operating | 4.2 km |
| Zonnepark Veenweg Ter Apel 2 | Power plant | 25.9 MW | Permitted | 4.2 km |
| Zonnepark Vlagtwedde II | Power plant | 132 MW | Permitted | 4.2 km |
| Rhede | Substation | — | — | 7.5 km |
| HGÜ DolWin3 Umspannwerk Dörpen West | Substation | — | — | 8.8 km |
| HGÜ DolWin2 Umspannwerk Dörpen West | Substation | — | — | 8.9 km |
| Electric boiler Ter Apelkanaal (Coöperatie Avebe) | CO2 emitter | — | Operating | 13 km |
| Papierproduktion Nordland | CO2 emitter | 244,460 tCO2e | — | 16 km |
| Green gas 2E Exloermond (Woagen) | CO2 emitter | — | Operating | 16 km |
Place
Other permit notices in Groningen
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-1821)
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-346281)
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-72161)
- Battery storage omgevingsvergunning application, Groningen (gmb-2026-411856)
- Battery storage omgevingsvergunning application, Het Hogeland (gmb-2025-285174)
- Battery storage omgevingsvergunning application, Midden-Groningen (gmb-2026-207772)
- Battery storage omgevingsvergunning application, Midden-Groningen (gmb-2026-302173)
- Battery storage omgevingsvergunning application, Oldambt (gmb-2025-500864)
Data on this page
- European Commission, Union Registry. EU Union Registry public data, CC BY 4.0.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.