| Fact | Value | Source |
|---|---|---|
| Location | Coevorden | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 28 Jul 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Wind | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.8293, 6.8086 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 303 power plants (236 operating, 3,926 MW), 101 substations, 25 CO2 emitters (16 operating) and 6 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Odoorn (BEE Stadskanaal) | Power plant | 4.16 MW | Operating | 6.1 km |
| Solar Odoorn (FP Lux Reio PV Netherlands Exloo) | Power plant | 10.9 MW | Operating | 6.1 km |
| Zonnepark Emmen | Power plant | 14 MW | Operating | 6.1 km |
| 110 kV Weerdinge | Substation | — | — | 7.2 km |
| 110 kV substation (OSM way/1117415162) | Substation | — | — | 7.2 km |
| 110 kV substation (OSM way/1117415161) | Substation | — | — | 7.2 km |
| Green gas 2E Exloermond (Woagen) | CO2 emitter | — | Operating | 15 km |
| Green gas Nieuweroord (Landbouwbedrijf Kloosterman) | CO2 emitter | — | Operating | 17 km |
| Electric boiler Gasselternijveen (Coöperatie Avebe) | CO2 emitter | — | Operating | 18 km |
Place
Other permit notices in Drenthe
- Battery storage omgevingsvergunning application, Assen (gmb-2025-106644)
- Battery storage omgevingsvergunning application, Emmen (gmb-2025-499288)
- Battery storage omgevingsvergunning application, Emmen (gmb-2026-230796)
- Battery storage omgevingsvergunning application, Hoogeveen (gmb-2025-125853)
- Battery storage omgevingsvergunning application, Hoogeveen (gmb-2026-51109)
- Battery storage omgevingsvergunning application, Midden-Drenthe (gmb-2026-24702)
- Battery storage omgevingsvergunning application, Midden-Drenthe (gmb-2026-374830)
- Battery storage omgevingsvergunning decision, Noordenveld (gmb-2026-161988)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.