Permit notice · Emmen, Drenthe, Netherlands
Data center omgevingsvergunning decision, Emmen (prb-2025-16423)
Data center omgevingsvergunning decision, Emmen (prb-2025-16423) is a permit notice in Emmen, Drenthe, Netherlands, published 7 Oct 2025, applied for by Teijin Aramid B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Emmen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 7 Oct 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | Teijin Aramid B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Data center | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.7750, 6.9070 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 294 power plants (216 operating, 3,916 MW), 100 substations, 20 CO2 emitters (14 operating) and 2 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Biomass Emmen (Emmtec Green Steam) | Power plant | 14.9 MW | Permitted | 0.3 km |
| Solar Emmen (Getec Park.Emmen) | Power plant | 7.88 MW | Operating | 0.3 km |
| 110 kV Emmen AKZO | Substation | — | — | 0.5 km |
| Energiepark Pottendijk | Power plant | 9.69 MW | Operating | 0.8 km |
| 110 kV Emmen Bargermeer | Substation | — | — | 1.9 km |
| 110 kV Weerdinge | Substation | — | — | 3.6 km |
| Green gas 2E Exloermond (Woagen) | CO2 emitter | — | Operating | 17 km |
| Green gas Coevorden (Bio Energy Coevorden) | CO2 emitter | — | Operating | 18 km |
| Electric boiler Ter Apelkanaal (Coöperatie Avebe) | CO2 emitter | — | Operating | 19 km |
Place
Other permit notices in Drenthe
- Battery storage omgevingsvergunning application, Assen (gmb-2025-106644)
- Battery storage omgevingsvergunning application, Emmen (gmb-2025-499288)
- Battery storage omgevingsvergunning application, Emmen (gmb-2026-230796)
- Battery storage omgevingsvergunning application, Hoogeveen (gmb-2025-125853)
- Battery storage omgevingsvergunning application, Hoogeveen (gmb-2026-51109)
- Battery storage omgevingsvergunning application, Midden-Drenthe (gmb-2026-24702)
- Battery storage omgevingsvergunning application, Midden-Drenthe (gmb-2026-374830)
- Battery storage omgevingsvergunning decision, Noordenveld (gmb-2026-161988)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.