Newton Energi Ltd holds 3 grid connections in the United Kingdom, with 199 MW of capacity between them.
Portfolio
The 3 assets and rights linked to Newton Energi Ltd, by class, with its role in each, across its 2 records.
- Grid connections3 · 199 MW
Grid connections 3 · 199 MW
| Grid connection | Location | Role | Capacity |
|---|---|---|---|
| Project Willow Bank grid connection | England, United Kingdom | Holder | 99.4 MW |
| Lowlands Farm grid connection | England, United Kingdom | Holder | 50 MW |
| NEL Alpaca grid connection | England, United Kingdom | Holder | 50 MW |
By country
Where the assets and rights are.
- The United Kingdom3 grid connections
Partners and counterparties
Owners, operators and grid operators on the same assets.
- Electricity North West Limited3 shared
Also recorded as
Sources name Newton Energi Ltd under 2 records; this page joins them. Links to any of them lead here.
| Name in the source | Identifier | Source |
|---|---|---|
| NEWTON ENERGI LTD | party:name:newton-energi-ltd | SP Electricity North West open data portal |
| NEWTON ENERGI LIMITED | party:name:newton-energi-limited | SP Electricity North West open data portal |
Own or advise on any of these assets, or looking to buy? Tell us; introductions are private.
Data on this page
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.