Heat plant · Leeuwarden, Friesland, Netherlands
Heat pump Leeuwarden (Bio LNG ECL)
Heat pump Leeuwarden (Bio LNG ECL) is a planned heat plant in Leeuwarden, Friesland, Netherlands, with 7.5 MW of capacity, operated by Bio LNG ECL B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Leeuwarden | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Status | Planned (SDE subsidy granted, not yet in use) | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Operator | Bio LNG ECL B.V. | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Capacity | 7.5 MW | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Technology | Heat pump | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Coordinates | 53.1972, 5.8044 | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
Research on this heat plant and its operator.Who owns it up to the parent company, who buys its heat, its permits and its subsidy, and an introduction to the operator.
How it compares
Heat pump Leeuwarden (Bio LNG ECL) is the 2nd-largest of 5 heat plants planned, permitted or under construction in Friesland and the 28th-largest of 43 in the Netherlands by capacity; its 7.5 MW is 1.4% of the 556 MW of heat plants planned, permitted or under construction we hold for the Netherlands. It is not built yet, so it is ranked among the heat plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| Friesland | 2nd of 5 | 28.8 MW | 26% |
| Netherlands | 28th of 43 | 556 MW | 1.4% |
Nearby
Within 50 km of this heat plant: 243 permit notices, 142 power plants (127 operating, 1,402 MW), 36 substations, 10 renewable fuel plants (7 operating, 46.1 MW), 5 data centers and 1 CO2 emitter (159,911 tCO2e), measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Renewable fuel Leeuwarden (Bio LNG ECL) | Renewable fuel plant | 17.8 MW | Planned | 0.0 km |
| Solar Leeuwarden (Zonnebult Leeuwarden-west) | Power plant | 3.9 MW | Operating | 0.0 km |
| Nitrogen natuurvergunning application, Leeuwarden (prb-2026-4306) | Permit notice | — | — | 0.5 km |
| Nitrogen natuurvergunning draft decision, Leeuwarden (prb-2026-13161) | Permit notice | — | — | 0.5 km |
| Nitrogen natuurvergunning draft decision, Leeuwarden (prb-2026-9454) | Permit notice | — | — | 0.5 km |
| 110 kV Leeuwarden | Substation | — | — | 1.0 km |
| Solar Leeuwarden (KBwinkels) | Power plant | 1.65 MW | Operating | 1.3 km |
| Solar Leeuwarden (Wetterskip Fryslân) | Power plant | 1.39 MW | Operating | 1.5 km |
| Scheelkampen | Substation | — | — | 1.7 km |
Operator and place
More from Bio LNG ECL B.V.
- Electric boiler Leeuwarden (Bio LNG ECL)5 MW · planned
- Renewable fuel Leeuwarden (Bio LNG ECL)17.8 MW · planned
Other heat plants in Friesland
- Biomass heat Sumar (Sonac Burgum)31.5 MW
- Biomass heat Joure (Koninklijke Douwe Egberts)12 MW
- Electric boiler Leeuwarden (Frieslandcampina Nederland)9.89 MW
- Biomass heat Leeuwarden (Snipperhout)1 MW
- Biomass heat Wier (N.V. Empatec)1 MW
- Heat pump Heerenveen (Ausnutria Operations)8.83 MW · planned
- Electric boiler Leeuwarden (Bio LNG ECL)5 MW · planned
- Heat pump Walterswald (Vastgoed Wâlterswâld)4.98 MW · planned
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.