Grid connection · Campbell County, Virginia, United States
Pigeon Run Solar and Storage grid connection (PJM AF2-404 - moved to TC1)
Pigeon Run Solar and Storage grid connection (PJM AF2-404 - moved to TC1) is a planned grid connection in Campbell County, Virginia, United States, connected by PJM Interconnection, L.L.C.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Campbell County (connects at Gladys DP-Stonemill 69 kV) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Status | Planned (engineering and procurement) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Technology | Storage | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Grid operator | PJM Interconnection, L.L.C. | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Queue date | 31 Mar 2020 | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Connection date | 1 Mar 2031 (proposed) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchLatest events
Dated events about this grid connection from official notices and registers, newest first. All recent changes.
- Entered the connection queue
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Due to connect
Grid operator and place
More from PJM Interconnection, L.L.C.
- Bruce Mansfield 345 kV grid connection (PJM C01-1243)2,500 MW
- Joshua Falls 765 kV grid connection (PJM C01-1390)2,300 MW
- Rockport - Jefferson 765 kV grid connection (PJM C01-1391)2,300 MW
- Rockport - Jefferson 765 kV grid connection (PJM C01-1392)2,300 MW
- Rockport - Jefferson 765 kV grid connection (PJM C01-1393)2,300 MW
- Sullivan 765 kV grid connection (PJM C01-1394)2,300 MW
- Sullivan 765 kV grid connection (PJM C01-1395)2,300 MW
- Flint Run 500 kV grid connection (PJM AG2-582)2,100 MW
Other grid connections in Virginia
- Joshua Falls 765 kV grid connection (PJM C01-1390)2,300 MW
- Cunningham - Elmont 500 kV grid connection (PJM C01-1111)1,694 MW
- Cunningham - Elmont 500 kV grid connection (PJM C01-1112)1,694 MW
- Bristers 500 kV grid connection (PJM C01-1884)1,000 MW
- CVOW 2, OSS 2 – T2G07 grid connection (PJM AF1-124 - moved to TC1)836 MW
- CVOW 2, OSS 2 – T2G07 grid connection (PJM AF1-124)836 MW
- CVOW 1, OSS 1 - T1L11 grid connection (PJM AF1-123 - moved to TC1)833 MW
- CVOW 1, OSS 1 - T1L11 grid connection (PJM AF1-123)833 MW
Data on this page