Grid connection · Young County, Texas, United States

Trinity Hills Wind repower grid connection (ERCOT 20INR0019)

Trinity Hills Wind repower grid connection (ERCOT 20INR0019) is a grid connection under construction in Young County, Texas, United States, held by Trinity Hills Wind Farm LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationYoung County (connects at 17002 Garvey Rd 345kV)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
StatusUnder construction (screening study completed, full interconnection study completed, interconnection agreement)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
HolderTrinity Hills Wind Farm LLCERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
TechnologyWindERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Grid operatorElectric Reliability Council of Texas, Inc.ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Queue date20 Jul 2017ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026
Connection date31 Dec 2026 (proposed)ERCOT GIS report · ERCOT Terms of Use · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue (the day the screening study started)

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

Other grid connections in Texas

All 1874 grid connections in Texas, United States